Holleman Bulgaria transports large number of Wind Turbine generators for Siemens Project
For the Siemens Project Sfanta Elena (Moldova Noua) – Holleman Bulgaria transported 21 complete units of Siemens 2.3 MW wind turbine generators and associated equipments from the port of Constanta to the windfarm site in Coroni - Sfanta Elena (Romania).
Details of the service contract for Holleman Bulgaria:
- Unloading from vessel in Constanta Port
- Components shifting inside the port
- Depositing the components in the port storage area
- Loading the barges in Constanta port
- River transport to Moldova Veche Port (Discharging Port)
- Depositing the components in the port
- Load and Carriage of the Cargo by road from Discharging Port to the Delivery Place
- Unloading at the hard stand on their own supports for nacelle and towers
- Blades, tower sections (for just in time deliveries) and all other components will be unloaded by cranes
- Civil Escort Vehicles
- Police Escorts